What a plant buys or outsources is part of its product. The customer does not care whether a coating fault happened inside the plant or at a provider. The responsibility stays with the plant, and so does the duty to control.
Who provides what
The example plant, a die caster with 260 employees, has 84 active external providers. Sorted by what they provide, the picture is clear.
| What is provided | Examples | Providers |
|---|---|---|
| Materials and components | Aluminum alloy, inserts, seals, packaging | 51 |
| Outsourced processes | Powder coating, anodizing, heat treatment, impregnation, shot blasting, overflow machining, washing, external X-ray | 9 |
| Services with an effect on the product | Calibration, die making and repair, freight, temporary staff | 24 |
The nine outsourced processes are the critical group. They are steps of the plant’s own value stream that happen under another roof. At the start, only 3 of the 9 providers had defined controls. For the other six there was a purchase order and trust.
Control by effect on the product
The plant set type and extent of control with one question: what happens to the product if this provider fails?
High effect: a failure reaches the customer or stops supply. This applies to coating, heat treatment and the alloy. Before the first order, the provider is approved with a check of the process, there is a written specification and an agreed change notification. During supply, every lot or batch is checked, and there is a yearly evaluation and a yearly visit.
Medium effect: a failure is found inside the plant. This applies to inserts, seals and overflow machining. Approval is by sample and questionnaire with a specification. During supply, the plant samples at receipt and evaluates once a year.
Low effect: no effect on conformity, as with office material and standard packaging. Commercial approval is enough, and the plant reacts only to problems.
Of the 84 providers, 17 need defined controls or a yearly evaluation. That is a list a purchasing department can keep.
What the order must say
Control starts with what the plant tells the provider. Every order to a high-effect provider names four things: the drawing revision, the specification, the records the provider has to send, and the criterion by which the plant will release the lot.
Evaluation with three figures
Once a year each listed provider is evaluated with three figures: conformity of deliveries, on-time delivery, and reaction to problems. The result is a score out of 100. Below 80, an action enters the plant’s action register, with the purchasing manager as owner.
The evaluation is deliberately simple. How suppliers are selected, scored and developed in depth is covered in the series on supplier management, and receiving checks in the series on incoming inspection. The management system needs to show three things: that providers are approved by a rule, that control fits the effect, and that the plant acts when a provider falls short.
The risk that stayed open
One point is not finished, and the plant says so. A high-effect provider must tell the plant before it changes its process: a new powder, a new oven, a new site. All high-effect providers have agreed to this in writing, except one coating provider.
In the list of risks this entry is still rated high. The management review decided that the clause is signed within eight weeks, or a second provider is approved. The deadline has passed and the action is overdue in the register, visible to everyone in the weekly review.
What changed in twelve months
All 9 outsourced processes now have a specification, an agreed check per lot and a named contact. Supplier on-time delivery rose from 86 to 92 percent, against a target of 93. A complaint about coating thickness, which used to return every few months, has not come back since the thickness is measured per lot at receipt.