Nonconforming Outputs and Corrective Action in One Register

How to contain and decide nonconforming product, when a corrective action is required and why closed must mean checked.

When something goes wrong, a plant has to answer two different questions. What do we do with this part? And what do we do so that it does not happen again? Mixing the two is the most common reason why problems return.

Six steps

The example plant of this series handles a nonconformity in six steps.

Contain. Stop, mark, separate. Check stock, work in progress and shipments for the same fault. Whoever finds it does this, together with the shift lead.

Decide. Rework, sort, scrap, use as is with permission, or return to the provider. An authorized person decides.

Record. What, where, how many, decision, cost. One report per event.

Ask whether a corrective action is required. By rule, not by mood.

Remove the cause. Find it, act on it, change the standard.

Check the effect. After a set time, with data: did it come back?

The first three steps are the correction. They deal with the parts. The last three are the corrective action. They deal with the cause.

The rule for corrective action

Without a rule, one of two things happens. Either every nonconformity gets a corrective action and none is finished, or none does. The plant set four triggers.

A corrective action is required when the nonconformity reached a customer, when the same fault occurred three times in three months, when one event cost more than EUR 2,000, or when an audit rated a finding as a nonconformity.

In all other cases the case is corrected and recorded. The monthly count shows when a small fault becomes due. The thresholds are the plant’s own choices. Yours will differ. What matters is that they exist.

One register

At the start, actions lived in four lists.

List Kept by Open Overdue
Findings of internal and external audits Quality manager 30 13
Actions from customer complaints Customer quality 14 6
Internal nonconformities and ideas Production 15 8
Minutes of the management review Assistant of the plant manager 5 2
Total 64 29

The plant merged them into one register with a few fields: source, process, what is to be done, type, owner, due date, status. The improvement coordinator keeps it.

Then came the routine that made the difference. Every week, in the management meeting, the coordinator shows the overdue actions per process owner. Nothing else. It takes a quarter of an hour.

Closed means checked

The register knows four states: open, in progress, done, effect checked. For a corrective action, only the last one counts as closed.

The check is planned when the action is defined: which figure, after how many weeks, by whom. The plant added this rule after 11 actions that had been reported as done came back as new nonconformities.

One field on the nonconformity report feeds the most telling figure of the whole system: was this cause known before, yes or no. At the start, 84 of 312 reports in a year said yes, which is 27 percent. More than a quarter of the plant’s problems were old acquaintances.

Twelve months later

The register holds 27 open actions, 4 of them overdue. The share closed by the due date rose from 55 to 85 percent. The average time to close a corrective action fell from 74 to 32 days. The plant wrote 236 nonconformity reports in the year instead of 312, and 26 of them had a known cause: 11 percent.

Where the methods live

This part describes the frame, not the craft. How causes are found is covered in the series on structured problem solving and on quality tools, and how customer complaints are handled in the series on complaint management. The management system adds what none of them can add alone: one place for every action, a rule for when a cause must be removed, and the proof that it was.