Changeover time drifts back when nobody looks, and a shorter changeover is worth nothing until the plan changes. This last part covers both: how to keep the time down and how to use it.
Four key figures per machine
| Key figure | Formula | Press P4 at the start |
|---|---|---|
| Average changeover time | Sum of minutes / number of changeovers | 96 minutes |
| Range | Longest minus shortest in the period | 53 minutes |
| Changeover share | Changeover minutes / planned minutes | 43 % |
| Interval of every part | Number of parts / changeovers per day | 3 days |
The range matters as much as the average. A large range means the method depends on the person and the day.
Three routines
- Every changeover: the setter puts a point on the chart at the machine, against the target line and the reaction limit. Above the limit, a reason is written on the same day.
- Every week: the supervisor reviews average, range and reasons with the team and agrees one countermeasure.
- Every month: the production manager observes one changeover against the standard.
On P4 the average fell from 96 to 68 minutes in four weeks, to 55 minutes in week six and to 29 minutes in week twelve. The range fell from 53 to 6 minutes.
Turn minutes into batches
The interval in which every part is produced once follows from the time available for changeovers.
Changeovers possible per day = minutes available for changeovers / changeover time. Interval in days = number of parts / changeovers per day. Average cycle stock = half the interval times the demand per day.
P4 loses 384 minutes per day to changeovers today. Keeping that time constant gives:
| Changeover time | Changeovers per day | Interval for 12 parts | Average cycle stock |
|---|---|---|---|
| 96 minutes | 4 | 3 days | EUR 54,000 |
| 68 minutes | 5 | 2.4 days | EUR 43,200 |
| 54.5 minutes | 7 | 1.7 days | EUR 30,900 |
| 29 minutes | 12 | 1 day | EUR 18,000 |
With 29 minutes, every part can run every day in less changeover time than four long changeovers cost before.
What changes in planning
- A fixed daily sequence of the parts. The order with the easiest transitions is found once and kept.
- Material is delivered to the machine in the rhythm of the sequence.
- Safety stocks are reviewed after three months of stable intervals, because shorter intervals react faster to demand changes.
- An urgent order waits one day at most, not three.
The trap
Planners who have fought for long runs for years will not cut batches on their own. The planning parameters in the system still carry the old lot sizes, and the old logic returns with the next plan. The sponsor decides the new interval, and the parameters are changed on a fixed date.
Roll out
The pilot is finished when the new time has held for three months and the batches have changed. Then the method moves to the machines with the same tool system, with the pilot team as trainers. From then on, every new tool and machine gets a changeover target in its specification: one height, one clamping edge, one locating system, no adjustment after mounting.
Quick changeover is one building block of flow. Leveling and pull systems build on the small batches it makes possible.