After stage 1, everything that is still done during the stop really needs the machine to stand, at least the way tools and settings are designed today. Stages 2 and 3 change the design.
Stage 2: convert internal to external
Some steps are internal only because conditions are created on the machine that could be created before.
| Internal today because | Convert by |
|---|---|
| Settings are found by trial | Fixed values per part number, stops, stored programs |
| Tools differ in size | Standard heights and interfaces with spacer plates |
| Conditions are created on the machine | Preheating molds, presetting tools, pre-assembling inserts |
| Quality is checked far away | Gauges and reference samples at the machine |
On press P4 four steps changed. All 12 dies were brought to one height with spacer plates, so the shut height is no longer adjusted: 6 minutes became 1. Feed length, pressure and cushion come from a settings sheet per part number: 9.5 minutes became 5. A go and no-go gauge at the press replaced the walk to the measuring room: 6 minutes became 2.
Together 13.5 minutes. The changeover falls from 68 to 54.5 minutes.
The settings sheet
One page per part number with every value the setter needs: tool number, shut height, feed length, pressure, cushion, speed, coil width and gauge number. When a setting is changed during a run, the sheet is changed on the same day. Settings that live in the head of one setter are found again by trial on every other shift.
Stage 3: streamline what remains
What is still internal is now done faster. Four principles cover most machines.
- Clamp without turning. A bolt holds with its last turn. All other turns are waste. Quick clamps, pear-shaped holes, U-washers or one-turn threads remove them.
- Locate without measuring. Pins, stops and V-blocks put the tool in position by its shape.
- Work in parallel. Two people on two sides halve the elapsed time of many steps.
- Eliminate adjustments. An adjustment is a setting that was not right the first time.
On P4, four hydraulic quick clamps replaced eight bolts: 12 minutes for loosening and tightening became 2. Two locating pins in the bolster replaced centering with a tape measure: 5 minutes became 1. With fixed settings the first part is good in nine of ten changeovers, so the second trial fell from 6 to 1.5 minutes. A second person takes over chute, strip and connections in parallel: 10.5 minutes of sequence became 3.5 minutes of elapsed time.
Together 25.5 minutes. The changeover falls from 54.5 to 29 minutes.
Low cost first
| Lever | Cost | Effect |
|---|---|---|
| Settings sheet per part number | A few hours | 4.5 minutes |
| Gauge at the press | EUR 1,000 | 4 minutes |
| Two people with a fixed sequence | Planning | 7 minutes |
| Standard die height and locating pins | EUR 4,200 | 9 minutes |
| Quick clamps | EUR 6,800 | 10 minutes |
Including two die carts, the plant invested EUR 15,000. It dropped the Saturday overtime on P4 and reduced stock, a benefit of EUR 41,400 per year. Payback: 4.3 months.
Safety comes first
Parallel work needs clear rules. One person has the control, nobody starts a movement without eye contact and a spoken signal, and energy is isolated according to the rules of the site before anyone reaches into the tool area. Quick changeover never shortens a safety step, and changes to clamping or guarding have to follow the machine documentation.