A workshop team achieves a 29-minute changeover on Thursday afternoon. On Monday the night shift needs 70 minutes again. Nothing was forgotten. It was simply never written down, trained and checked.
What the standard contains
The changeover standard is the best known sequence, on one page at the machine.
| Element | Content |
|---|---|
| Header | Machine, tool family, target time, reaction limit, version and date |
| Sequence per person | Step, minutes, cumulative time, key point, safety note |
| Photos | Clamping points, connections, positions of cart and tools |
| Preparation checklist | External steps before the stop, with signature |
| After the restart | Return and check of the old tool, cart check, log entry |
A key point is the detail that makes the step safe, right or easy: which clamp first, which mark the die must touch, which value to read back aloud.
Two people, one sequence
The standard of press P4 fits into six blocks.
| Time | Setter | Second person |
|---|---|---|
| 0 to 3 | Stop, open clamps, release strip | Remove chute and bins, cut strip |
| 3 to 8 | Pull old die onto cart, clean bolster | Rewind coil, swing in new coil |
| 8 to 12 | Push new die against pins, close clamps | Connect air and sensors, mount chute and bins |
| 12 to 19 | Thread strip, enter values from the settings sheet | Check values against the sheet, place gauge |
| 19 to 27 | Trial strokes, first parts | Gauge three dimensions, sign first part |
| 27 to 29 | Release, ramp to full speed | Take old die away, check cart |
The elapsed time of each block is the longer of both columns. Where one person waits, work can still be moved to the other side.
The changeover cart
Every tool for the changeover has a fixed place on a cart or a shadow board at the machine: wrenches, spacer blocks, cleaning cloths, the gauge, the checklist. The cart is never borrowed. After the restart, the setter checks that it is complete. A missing wrench found at 02:00 costs more than the cart.
Training in four steps
- The trainer shows the standard and a video of a changeover done to the standard.
- The trainer does one changeover and explains the key points.
- The setter does it twice with the trainer beside him.
- The setter does it alone, and the trainer measures.
Then the skills matrix is updated. It shows for every shift who can change over the machine alone and who can train others. The training is repeated after every change of the standard.
Keeping the standard alive
- Update within one week. When an improvement works, the standard is changed and the old version is removed from the machine.
- Record deviations. A changeover above the reaction limit gets a reason on the same day.
- Audit monthly. The production manager observes one changeover against the standard and checks the checklist and the cart.
The effect of a standard shows first in the range, not in the average. On P4 the difference between the shortest and the longest changeover fell from 53 to 15 minutes within four weeks, before any investment was made. A stable changeover is one that planning can count on, and that is the condition for cutting the batches.