SMED and Changeover Reduction | Part 3 of 6

Separating Internal and External Setup Work

Stage 1 of SMED moves preparation and cleanup out of machine downtime. On the example press it cuts 28 of 96 minutes without investment.

The first stage of SMED does not make any step faster. It only changes when the step is done. That sounds modest, and it regularly removes a third of the changeover time.

Two kinds of work

  • Internal work needs the machine to stand: removing the old tool, mounting the new one, connecting, the first parts.
  • External work can be done while the machine runs: fetching the next tool, tools and material, the paperwork, and afterward cleaning and storing the old tool.

In an unorganized changeover, nearly everything is done while the machine stands. The setter stops the press and then starts to look for the order, the wrenches and a forklift.

Three questions for every step

Go through the step list and ask:

  1. Could this be done before the machine stops? Then it is external, before.
  2. Could this be done after the machine runs again? Then it is external, after.
  3. Does the machine have to stand for it today? Then it stays internal for now.

Stage 1 on press P4

Five of the 22 steps moved out of the stop.

Step New rule Minutes
Get order and setup sheet from the office Supervisor hands both over 30 minutes before the stop 4.0
Search wrenches and spacer blocks A changeover cart with all tools stays at the press 5.0
Fetch the next die, wait for the forklift Die on a cart beside the press before the last part, forklift booked 8.0
Take the old die to storage Done after the restart 5.0
Fetch the new coil, wait for the crane Coil pre-staged on the second decoiler arm 6.0

Together these are 28 minutes. The changeover falls from 96 to 68 minutes without a single change to the press or the dies.

The preparation checklist

External work only happens reliably when it is written down. The checklist for P4 has seven lines: order and setup sheet at the press, next die checked and on its cart, next coil staged, changeover cart complete, empty bins and labels, gauge for the next part, second person informed.

It is signed before the stop. An unsigned checklist means the changeover does not start. That rule sounds strict, and it is what turns a good intention into a routine.

What makes it hold

  • A signal. The plan shows the time of the next changeover, and the board at the press shows who prepares.
  • A place. Marked floor areas for the next die, the old die and the changeover cart.
  • Booked transport. Forklift and crane are planned with the changeover time. Nobody waits for them while the machine stands.
  • A checked tool. Dies are inspected and repaired after the run. A die that is found damaged at the next changeover turns external work back into internal work.

The picture to keep in mind

Think of a pit stop in racing. When the car arrives, the tires, the tools and the crew are already in position. Nobody goes to fetch a wheel after the car has stopped.

When the machine stops, everything and everyone needed is already there. Whoever still has to fetch something has started too late.

After stage 1, the remaining 68 minutes are real internal work. The next two stages make that work shorter.