The sales price of a valve housing is EUR 42.00. What does it cost to make? The answer is not in the ERP system as one number. It is a calculation that follows the routing, and every line of it is something operations influences.
Along the routing
| Element | Basis | EUR per part |
|---|---|---|
| Material | One casting | 14.20 |
| Machining | 0.16 h at EUR 37.15 | 5.94 |
| Operator | 0.16 h at EUR 18.15 | 2.90 |
| Setup | 1.5 h at EUR 73.45 per lot of 400 | 0.28 |
| Assembly and test | 4 minutes at EUR 36.30 | 2.42 |
| Scrap | 3.0 % of input | 0.80 |
| Plant overhead | 20 % of conversion cost | 2.31 |
| Manufacturing cost | 28.85 |
Conversion cost is everything between material and finished part: machining, operator, setup, assembly and test, here EUR 11.54. The overhead covers planning, quality, maintenance management and administration.
Scrap is a cost line, not a footnote
At 3 percent scrap, every good part carries EUR 0.80 for the parts that were lost. That is almost three times the setup cost per part. Many calculations hide scrap in an overhead rate or ignore it. Then nobody sees that quality is the larger lever.
Which lever matters most?
Change one input at a time and recalculate:
| Lever | Change | Cost per part | Effect |
|---|---|---|---|
| Cycle time | 0.16 to 0.14 h | 27.49 | minus 1.36 |
| Scrap | 3.0 to 1.5 % | 28.44 | minus 0.41 |
| Setup | 90 to 30 minutes | 28.61 | minus 0.24 |
| Casting price | 14.20 to 14.90 | 29.57 | plus 0.72 |
Two lessons come out of the table. First, cycle time on the main machine is worth more than any setup project. Second, a 5 percent higher casting price costs three times what cutting setup time by two thirds saves. Purchasing and operations need to look at the same calculation.
Keep it real
A calculation is only as good as its inputs. Three checks keep it honest:
- Real routing. If the operators use a different sequence or time than the system, use theirs and correct the system.
- Real scrap. Use the scrap rate of the last six months, not the planned one.
- Real lot size. If lots are split in practice, the setup cost per part is higher than calculated.
Recalculate the top ten products once a year and whenever the routing, the machine or the supplier changes. Sales uses the same rates for quotes, so a wrong rate on the shop floor becomes a wrong price at the customer.
From cost to decision
The calculation is not an accounting exercise. It shows in euros where the next improvement should go, and it gives every number on the shop floor board a price.