The machining area spent EUR 447,609 in March. The budget was EUR 434,713. Is the area EUR 12,896 over budget?
Not necessarily. The budget was planned for 13,000 good parts. The area produced 12,600. Comparing the two numbers mixes the effect of volume with the effect of performance, and the discussion that follows goes nowhere.
Flexing in four steps
- Plan volume. From the sales and operations plan: 13,000 good parts in March.
- Standard cost. Quantities and rates per part from the product calculation.
- Flex. Variable costs at actual volume, fixed costs at plan.
- Compare. Actual against the flexed budget.
| Cost line | Flexed budget | Actual | Variance |
|---|---|---|---|
| Material including scrap | 184,464 | 199,660 | 15,196 |
| Direct labor | 67,032 | 72,716 | 5,684 |
| Energy and tools | 16,380 | 16,900 | 520 |
| Fixed costs | 158,333 | 158,333 | 0 |
| Total | 426,209 | 447,609 | 21,400 |
At actual volume the area should have spent EUR 426,209. It spent EUR 21,400 more. That is the performance question. The lower volume is a separate topic, and it belongs to sales and planning.
Build it from the bottom
A budget that operations can steer is built from volume, routings, rates and headcount, not from last year plus 3 percent:
- September: volume plan per product family and month.
- October: hours and headcount from routings, productivity targets and absence.
- October: wage increases, energy contracts and material prices from HR, purchasing and controlling.
- November: budgets per cost center, agreed with each owner.
- December: approval by plant management.
The owner who agreed to the budget can explain the variance later. An owner who received a top-down number cannot.
Write improvements into the budget
Planned savings belong in the budget as separate lines with owners and start months, for example “Scrap VH-40 from 3.0 to 1.5 percent, EUR 64,700 a year, from July.” Then they are visible, and the monthly comparison shows whether they arrive.
Forecast, not only budget
The budget is fixed for the year. The forecast is not. Every quarter, update expected volume, prices and costs for the remaining months. The useful question in the review is not “Are we on budget?” but “Where will we land, and what can we still change?”
The payoff
A flexed budget turns the monthly cost meeting from a defense into an analysis. The next step is to split the remaining EUR 21,400 by cause, and that is the topic of the next part.