Quality Management System | Part 2 of 12

Context, Interested Parties and Scope on One Page

How a management team writes down who expects what, what changes around the plant and what the system covers, in two hours.

Many manuals open with twenty pages on the company, its history and its environment. Nobody reads them, and nothing follows from them. The same content fits on one page, if it is written by the management team itself and if every line leads somewhere.

The page answers three questions. Who expects something from us? What changes around us and inside? And what does the system cover?

Who expects what

Standards for management systems speak of interested parties. In plain words: who can be disappointed by this plant, and how would we notice?

The management team of the example plant, an aluminum die caster with 260 employees, wrote one line per party.

Who What they expect, in one line How we know
Customers Conforming parts on the agreed day, fast answers Complaints, delivery figures, scorecards
Owners A return and no surprises Monthly report
Employees Safe, clear work and the chance to qualify Turnover, talks, qualification plan
Suppliers and outsourced processors Clear specifications, forecasts, payment on time Supplier talks
Authorities Permits and laws are respected Legal register, inspections
Certification body An effective system, shown with evidence Audit reports

The third column is the useful one. Wherever the team could not say how it would notice a failure, there was a gap. For suppliers, for example, the plant had no regular talk at all. It learned about their dissatisfaction when a delivery was late.

What changes

The second part of the page lists what is changing around the plant and inside it. Six to eight points are enough. The example plant wrote down six: two customers stand for 58 percent of sales, customers ask for full traceability of each housing, setters for casting cells are hard to find, three of six casting cells are older than twenty years, energy cost is volatile, and a new ERP system is planned in eighteen months.

The rule for this list is strict. Each point leads to a risk, an objective, a requirement in a process, or nothing. The shortage of setters became an objective: critical roles with a trained deputy. The traceability demand became a requirement that is checked in every order review. Energy cost has no effect on whether a housing conforms, so it was noted and not followed in this system. A list that leads to nothing is not needed.

The scope in three sentences

The scope says what the system covers: products and services, sites, processes. The example plant wrote:

“Development of casting and machining processes, die casting, machining and assembly of aluminum housings to customer drawings at our one site. All fourteen processes of the plant are included. Product design is not applicable, because every part is made to a customer design.”

Three rules of thumb help.

Everything that is sold under the name of the site belongs in. A product line cannot be left out because it is difficult.

Outsourced processes stay in scope. The plant sends housings out for coating and heat treatment. It does not do the work, but it answers for the result, so it controls these processes at the provider.

What is left out needs a reason that a stranger would accept. “We do not design products, our customers do” is such a reason. “We did not get to it” is not.

How to run the session

Two hours, the management team, a wall and cards. No slides.

Keeping it alive

The page is reviewed once a year, and it is the first input of every management review. When a new customer requirement, a law or a technology arrives, it is added there first and then handed to a process owner. That is all the upkeep it needs.