Skip to content
Quality Management System | Part 3 of 12

Quality Policy and Measurable Quality Objectives

How to write a policy that can be quoted and six objectives with a number, a date and an owner.

Walk through a plant and ask ten people what the quality policy says. Most will point to a frame on the wall. Ask what the quality objectives are, and the answers get quieter. In the example plant of this series, 9 of 30 employees could name a single quality objective.

A policy that can be quoted

A policy that could hang in any plant says nothing about yours. A useful policy is short, says what the plant will and will not do, and contains a promise of management to the employees.

The management team rewrote the page into four sentences:

“We deliver what was agreed: the part, the date and the documents. We accept only orders we have checked. We stop and report when something is wrong, and nobody is blamed for reporting. We measure six objectives and act when one is off.”

Each sentence has a consequence. The second one means that sales may not confirm an order before feasibility and date are checked. The third one is a promise that management has to keep in front of the team, on the day a shift lead blocks a lot that was due for shipping.

The policy is explained, not only posted. Each supervisor explains it in the shift meeting with one example from the area.

Six objectives

Objectives without numbers cannot be missed, and therefore cannot be reached. The plant replaced eleven objectives with six.

Objective Measure Start Target
Fewer customer complaints Complaints accepted per year 58 35
Less scrap and rework Cost in percent of sales 3.1 2.6
Deliver on the agreed day Order lines on the confirmed date, percent 88 95
Finish what we start Corrective actions closed by the due date, percent 55 85
Solve problems once Nonconformities with a cause seen before, percent 27 12
No role depends on one person Critical roles with a trained deputy, percent 62 90

Four rules

A number, a date, an owner. The owner is a process owner, not a department. Complaints and delivery belong to the process that ships and serves customers, scrap to production, the two action figures to the improvement coordinator, the deputies to human resources.

Few. Six objectives on one page are reviewed every month. Twenty are filed.

Linked to a process. Each objective is also a key figure in one process profile. That way somebody works on it every month, not only before the management review.

From objective to plan

An objective without a plan is a wish. For each one, the plant wrote down four things: what will be done, who does it with which resources, by when, and how the result is checked.

For scrap and rework this meant: the top five scrap causes per casting cell are worked on every week, and the first-part release is recorded on every shift. The production manager answers for it, with one process engineer for two days a week and EUR 15,000 for sensors on two cells. The target is 2.6 percent on average over twelve months. Controlling reports the figure every month.

What happened

After twelve months the plant counted 31 complaints, 2.6 percent scrap and rework, 94 percent on-time delivery, 85 percent of actions closed on time, 11 percent repeat nonconformities and 92 percent of critical roles with a deputy. Five of six objectives were reached. On-time delivery missed its target by one point and became the first topic of the management review, which decided on a second leak test bench.

And on the shop floor, 26 of 30 employees could name a quality objective. Nobody had learned a page by heart. Each area simply had one number on its board that it could influence.

Newsletter

One Lean idea.
Every two weeks.