Workforce Planning and Shift Scheduling | Part 5 of 8

Qualification in the Staffing Decision

How to set a minimum coverage per station, read the gaps before the roster is built, and decide which stations a night shift can run.

A roster that ignores qualification is a list of names, not a plan. It works until the one person who can run the test station takes a week of vacation.

Minimum coverage per station

The rule in A2 is simple enough to apply without a meeting: one qualified person per shift plus one reserve. A station in two shifts needs three people at level 3 or higher, a station in three shifts needs four.

Station Shifts Needed at level 3 or higher Qualified today Gap
S1 Rotor pre-assembly 3 4 9
S2 Stator insertion 3 4 7
S3 Housing assembly 3 4 11
S4 Gear unit assembly 2 3 5
S5 Final assembly 2 3 8
S6 Electrical test 2 3 2 1
S7 Leak and run-in test 2 3 3
S8 Packing and labeling 3 4 12

Levels, assessments and training records belong to the qualification matrix of the area, a subject of its own. The staffing plan needs the count per station and the rule that the roster places nobody below the minimum level.

Three figures that steer

Coverage per station. The count in the table above against the minimum. One gap in A2: station S6 has two qualified people and needs three.

Stations per person. The 21 employees hold 57 entries at level 3 or higher, which is 2.7 stations per person against a target of 3.5. Versatility is what makes a floater possible, and it is built in the valley months.

Single points of failure. Stations with fewer than two qualified people. The target is zero, and in A2 it is met, which is the difference between a gap and an emergency.

The qualification plan that follows

Gap Action Who By
S6 test: 2 qualified, 3 needed Train two people to level 3, so the station also has a reserve Shift leader with the trainer of S6 Week 8
Stations per person at 2.7 Every employee learns one further station in the valley months Area manager Month 12
Night crew: only 4 hold level 3 on all four night stations Bring all six people of crew C to level 3 on S1, S2, S3 and S8 Area manager Before go-live

Train two where one is missing. A station that is brought exactly to its minimum is one resignation away from the same problem.

Qualification decides which stations run at night

The night shift in area A2 runs four of the eight stations. Which four was not an arbitrary choice. Rotor pre-assembly, stator insertion, housing assembly and packing have nine, seven, eleven and twelve qualified people, the deepest coverage in the area. Electrical test, with two, is the thinnest and stays on the day shifts, where a shift leader and a trainer are present.

The second reason is material flow: those four stations feed the day shifts through a buffer, so a short stop at night does not stop the line in the morning. Capacity, qualification and flow point at the same four stations.

Qualify first, roster second

The order matters more than it looks. A pattern that needs a qualification the area does not have yet fails in week one, and it takes the credibility of the whole plan with it. The qualification plan runs before the model goes live, the coverage table is reviewed every month, and every new employee gets a fixed learning path: station, trainer, duration, assessment and an entry in the matrix.

That is four lines of administration per person, and the difference between a roster published three weeks ahead and one rebuilt every morning at 06:45.