Workforce Planning and Shift Scheduling | Part 6 of 8

Peaks and Valleys: The Order of Measures

How to plan the requirement month by month, order the measures for peaks by cost and lead time, and use a working time account instead of overtime.

A year is not twelve equal months. Areas that plan only the annual requirement meet their peaks in the week they arrive, when only the most expensive measures are left.

The requirement per month

Capacity is the operating days of the month times 150 attendance hours per day, the hours of the chosen model. Required hours come from the monthly program at 90 percent utilization.

Month Operating days Required hours Capacity hours Gap
July 22 2,800 3,300 -500
August 18 2,000 2,700 -700
September 22 3,250 3,300 -50
October 22 3,400 3,300 +100
November 21 3,250 3,150 +100
Year 250 35,000 37,500 -2,500

Two months of the year are above capacity, by 100 hours each, and the valley in July and August is 1,200 hours. That is not a hiring problem. It is 200 hours to move from summer to autumn.

The ladder

The measures for a peak are written down once, in a fixed order, with cost per hour and lead time, and the list hangs on the wall before the peak arrives.

No. Measure Lead time EUR per hour
01 Move the plan into a valley Same week 0.00
02 Build up the working time account Same day 38.00
03 Move qualified people between areas 1 week 38.00
04 Overtime beyond the account Same week 47.50
05 Saturday shift 2 weeks 47.50
06 Agency labor 4 weeks plus 3 to qualify 46.00
07 Sunday or additional shift 3 weeks 57.00
08 New shift model or new head count 3 to 6 months 38.00

The rates are example values. Build the ladder with your own figures: the point is the order, not the number. Most areas start at step 04 and never find out that steps 01 to 03 would have carried the year. Two entries deserve caution. Agency labor looks cheap per hour and is not fast: four weeks to get people, about three more before they reach full output, and only on stations with a short learning curve. A new model is cheap per hour and slow to reverse.

The working time account

An account turns a yearly peak into a monthly balance. It needs a band, a rule and a visible figure.

In A2 the band is minus 40 to plus 80 hours per employee, an example value. Across 26 people that is 2,080 hours upward. Build-up is capped at ten hours per week and announced with the roster, reduction happens in whole days in the valley months, and balances are reviewed monthly. The area builds about 1,200 hours in summer and carries the 200 hours of the autumn peak out of them: ten percent of the band.

What the balances tell you

Sign to watch What it means What to do
Balances drift to the upper limit The account is permanent extra capacity Recalculate the head count
Balances drift to the lower limit The program is below the staffing level Move work in, or plan training
A few people carry most of the balance The same, usually most qualified, people are always asked Close the qualification gaps, balance the build-up by rule
Balances expire unused Nobody plans the reduction Plan reduction days with the vacation calendar

Bands, expiry rules, insolvency cover and the co-determination around an account belong to human resources and the employee representation, not to a planning method. Agree them before the first hour is booked.