Changeover Share and EPEI Calculator
Every part every interval: how often you can run all part variants with the time that demand leaves for changeovers.
Enter your figures and select Calculate. The fields are prefilled with a worked example.
How to read it
How it was calculated
Please confirm your newsletter subscription via the link in your inbox.
The formula
Use this calculator when you want to know how small your lots can get with the current changeover time and capacity.
Time for changeovers = Available time - Run time for the daily demand
Changeovers per day = Time for changeovers / Changeover time
EPEI = Number of part variants / Changeovers per day
Changeover share = Time for changeovers / Available time
Worked example
Inputs
- Available production time per day: 900 min
- Run time needed for the daily demand: 780 min
- Average changeover time: 30 min
- Number of part variants: 12 parts
Calculation
- Time for changeovers = 900 min - 780 min = 120 min per day
- Changeovers per day = 120 min / 30 min = 4
- EPEI = 12 parts / 4 changeovers per day = 3 days
- Changeover share = 120 / 900 = 13.3%
- Average cycle stock = 3 days / 2 = 1.5 days of demand
Result
EPEI: 3 days. Each of the 12 parts can be produced every 3 days, so one lot has to cover 3 days of demand. An interval of a few days is workable, but every day of interval is a day of stock. Halving the changeover time to 15 minutes would cut the interval to 1.5 days without any extra capacity.
How to read the result
- The interval is a result of changeover time and free capacity, not a planning preference. To make smaller lots, shorten the changeover or free up capacity.
- Use the gain from shorter changeovers for more changeovers, not for longer runs. Only then inventory and lead time fall.
- The calculation assumes that all parts run once per interval. High runners can run more often and rare parts less often: the average stays the same.